Village not safe or ready: Chiller statement

24 July 2016

Statement for Australian Team Chef de Mission Kitty Chiller

TEAM: Due to a variety of problems in the Village, including gas, electricity and plumbing I have decided that no Australian Team member will move into our allocated building (B23).

I will reassess the situation this evening. 

For over a week now AOC staff have been working long hours to get our section of the Village ready for our athletes.

Problems include blocked toilets, leaking pipes, exposed wiring, darkened stairwells where no lighting has been installed and dirty floors in need of a massive clean.

In operations areas water has come through the ceiling resulting in large puddles on the floor around cabling and wiring.

We have raised our concerns on a daily basis with the Organising Committee and the IOC, especially at the daily Chef’s meeting.

We are not alone, our friends from Team GB, New Zealand and others are experiencing the same problems in their accommodation.

We have been pushing hard for a solution.

Extra maintenance staff and over one thousand cleaners have been engaged to fix the problems and clean the Village but the faults, particularly the plumbing issues have not been resolved.

Last night (Saturday), we decided to do a “stress test” where taps and toilets were simultaneously turned on in apartments on several floors to see if the system could cope once the athletes are in-house.

The system failed. Water came down walls, there was a strong smell of gas in some apartments and there was “shorting” in the electrical wiring.  

We were due to move into the Village on 21 July but we have been living in nearby hotels, because the Village is simply not safe or ready.

Our staff are continuing to setup as best they can for the arrival of the athletes. For those athletes arriving in the next three days we have made alternative accommodation arrangements.

We welcome a decision by the IOC to recommend to the Organising Committee that stress tests be carried out throughout the Olympic Village.

The IOC has recommended 1. A plumbing stress test and 2. A fire safety test.

Those tests will include all floors, all rooms, all fixtures, sinks, showers and toilets. As well as fire alarms, lighting in stairwells and exits.

Representatives from National Olympic Committees (NOCs) have been invited to observe the test.

From an AOC point of view, John Coates, has always stressed that for a Games to be successful, you need to get 3 things right, the athlete’s Village, the transport and the food.

There is much work to be done at the Village and we appreciate the efforts of the IOC and the RIO Organising Committee to “push things along” and solve the problems.

AOC

Related News

Willett equals world record and claims two golds at ISSF World Cup

Willett equals world record and claims two golds at ISSF World Cup

21 March 2019

It has been an outstanding weekend for James Willet at the ISSF World Cup in Acapulco, Mexico where he produced exceptional results in both men’s and mixed trap, equalling a world record and claiming two gold medals.

Jandakot delivers world champs qualifiers and several PB's

Jandakot delivers world champs qualifiers and several PB's

19 March 2019

Athletes responded to the perfect conditions at the Jandakot Airport Track Classic with world championships qualifiers, an Australian record and numerous personal bests.

Chalmers and Campbell find golden hattrick at 2019 NSW State Champs

Chalmers and Campbell find golden hattrick at 2019 NSW State Champs

19 March 2019

It was raining gold for Australia’s Olympic swimmers at the 2019 NSW State Championships, with 12 Olympians finding a place on the podium over the three-day event and Australia looking poised for Tokyo 2020 success.

Related Games

Rio 2016

Rio 2016